ENABLING WORKS

Travelodge Scarborough

Client | Travelodge

Location | Scarborough

Timing | 24 Weeks

Project Overview

Sloane Curtis successfully delivered the enabling works at St Nicholas Travelodge in Scarborough.

Internally, the works included a basement strip-out, floor and wall repairs to a hallway and bedroom 114, and repairs to the staircase serving the first and second floors. These existing areas had been affected by significant damp, resulting in deterioration and rot.

The project also involved the decommissioning of the existing swimming pool. Extensive drainage works were undertaken, followed by the installation of fireproof compartmentation to leave the area safe and secure.

The works also covered extensive internal light-well roof repairs and renewal, including installation of structural scaffold.

Additionally, externally, a new roof was installed to the front entrance canopy, forming part of six new roof areas delivered across the building. Further structural works included the construction of a new retaining wall and concrete infill works to the front elevation.

Scope of Work

Basement strip-out, floor repairs, wall repairs, staircase repairs, roof & canopy repairs, new roof installations, structural work, concrete infills, fire boarding, guano removal, swimming pool decommissioning.

Challenge

One of the main challenges was the restricted site logistics. With only a single route available for access into and out of the building, all materials and waste had to pass through the same area. Initially, much of the waste was being moved manually, which increased the amount of handling required and affected the efficiency of material movements throughout the site.

Solution

To improve productivity, the site team introduced heavy-duty tubs to transport waste through the building. This allowed larger quantities of waste to be moved safely on each journey, reducing the number of trips required and improving the overall flow of materials and waste through the restricted access route.

Outcome

The project was successfully completed two weeks ahead of programme.

Through the various repairs and replacements, we addressed the existing defects and improved the building’s overall long-term condition and structural integrity. The works were also carried out within a live hotel environment, demonstrating our ability to operate safely around hotel staff and members of the public.